Last reviewed November 2026.
Osceola County driveway permits
In unincorporated Osceola County, which takes in Harmony, Narcoossee, Ashton and Holopaw, two short paragraphs of the county code govern driveways. Section 22-50.6 reads: "(a) Residential driveways shall not exceed twenty-four (24) feet in width unless approved by conditional use. (b) Residential driveway construction or widening shall be authorized by the issuance of a driveway permit by Osceola County."
That makes widening a driveway a permitted job in its own right, and the 24 foot cap is the number that decides how wide a driveway extension can be at the street.
The apron, sidewalks and culverts
| Item | County requirement |
|---|---|
| Driveway concrete, edge of pavement to right-of-way line | 6 in deep, wire mesh or fiber mesh throughout; forms the same depth as the pour |
| Sidewalk | Class NS concrete, 4 in thick, 3,000 psi at 28 days |
| Sidewalk where it crosses a driveway | At least 6 in of Class I concrete with 6 x 6 in wire mesh or fiber mesh |
| Concrete over a driveway culvert | At least 4 in over the pipe, increasing to 6 in at the roadway edge |
| Driveway culvert pipe | RCP, HDPE or corrugated metal, with mitered end sections |
Source: Osceola County Board of County Commissioners Road Construction Specifications (August 2015, updated March 31, 2025).

Slabs, sheds and the building office
The county Building Office's list of residential work that needs a permit includes a slab with footers, a shed or storage building, a pool and pool screen enclosure, a screen room and a pergola. The fee appendix (Resolution 24-062R, effective October 1, 2024) sets these lines:
| Item | Fee |
|---|---|
| Slab with footer | $60 plan review + $60 permit |
| Residential slab permit review, zoning (adding a slab to a developed site) | $20 flat |
| Failure to obtain a permit before work begins | $80 + double the normal permit fee |
Source: Osceola County Appendix A, Building Permit and Related Fees, effective October 1, 2024. Building Office: 1 Courthouse Square, Suite 1400, Kissimmee; 407-742-0200.
A detached garage or barn slab is part of that building's permit; the concrete slab page covers the termite treatment and vapor retarder that go with it.
The $7,500 exemption in the county
Osceola County's permit page says that from July 2026 it implements the building permit exemption from HB 803, the 2026 law behind Section 553.79(1)(g). Excluded: structural, electrical, plumbing, mechanical and gas work, and work on properties partly or entirely in a flood hazard area. Requests go to the Building Office on its Owner Disclosure of Exempt Work form. The exemption covers building permits only; a driveway permit under Section 22-50.6 is a separate requirement.
Driveways onto US 192 and US 441
Rural lots east of St. Cloud often front a state highway. A driveway connecting to one needs a connection permit from the Florida Department of Transportation: Rule 14-96.003 says no one may construct, relocate or alter a connection without first obtaining one, regardless of other governmental permits. The Holopaw page covers the rural-lot details.